Preconstruction Process

From first meeting to signed contract

We’ve developed a methodical approach to preconstruction that brings clarity, alignment, and confidence to our projects. What happens intentionally during design creates the foundation for a successful build.

Before we start the demo or break ground, we help you understand the path ahead, connect you with the right design professionals, and shape a scope that reflects your goals and investment priorities.

Our process is thorough, but flexible. Some clients prefer a detailed view. Others just want to know we’ve got it handled. Either way, we guide the journey from early exploration through design development, budgeting, and contract readiness—so construction begins with clarity.

Preconstruction Timeline at a Glance

From first meeting to signed contract

01_Client_Introduction_and_Exploration_Meeting

Client Introduction & Exploration Meeting

Duration: 60–90 minutes
Purpose: Align on values, goals, financial investment and fit
→ Review sample Preconstruction Services Agreement

02_Sign_Preconstruction_Services_Agreement

Sign Preconstruction Services Agreement

Duration: Throughout the design phase
Purpose: Engage Opus as build consultant during design
→ Hire your architect and/or interior designer

03_Site_Meeting_with_Owner_and_Design_Professional

Site Meeting with Owner & Design Professional

Duration: 60–90 minutes
Purpose: Walk site or review drawings, align on feasibility and communication

04_Opus_Consulting_Services

Opus Consulting Services

Duration: Pace set by client & design pro, usually several months
Purpose: Support design team with constructability, pricing guidance, and trade input
→ Preliminary pricing, advance into construction documents

05_Permit_Acquisition

Permit Acquisition

Duration: Varies by jurisdiction
Purpose: Submit and secure required permits while design work continues

06_Completion_of_Construction_Documents_and_Finishes_Schedules

Completion of Construction Documents & Finishes Schedules

Duration: Pace set by client & design pro, usually several months
Purpose: Produce detailed, buildable drawings and selections
→ Confirm CD set is ready for Trade Walk

07_Trade_Walk

Trade Walk

Duration: 4–8 hours (plus ~2 weeks for trade proposals)
Purpose: Trade partners review drawings/site, identify challenges, generate proposals

08_Post_Trade_Walk_Consultation

Post Trade Walk Consultation

Duration: 1-2 hours
Purpose: Address new details uncovered, confirm scope implications

09_Phasing_(After_Budgets,_if_needed)

Value Engineering / Phasing (After Trade Walk, if needed)

Duration: Varies
Purpose: Adjust scope in response to trade input, keep project in target range

10_Construction_Budgets

Construction Budgets

Duration: ~3 week after trade walk
Purpose: Prepare transparent cost-plus budget (or consider fixed price)

11_Phasing_(After_Trade_Walk,_if_needed)

Value Engineering / Phasing (After Budgets, if needed)

Duration: Varies
Purpose: Align final scope with investment goals once budget is clear

12_Finalize_Drawings_and_Selections

Finalize Drawings & Selections

Duration: Varies by revisions
Purpose: Update drawings and finishes schedules after VE/phasing
→ Lock scope with final drawings

12_Finalize_Drawings_and_Selections

Sign Construction Contract

Duration: Usually ≥2 weeks before construction starts
Purpose: Secure schedule, coordinate trades, materials, permits
→ Transition into construction

You don’t need to manage this process—we will. Whether you want to stay close to the details or simply trust the structure, we’ll guide the journey.